In this section of cable installations, we provided a step by step process of pulling the cables from the media box to its destination area. The estimated time to complete the cable installation is 8 hours with 3 people for 12 cables.
*NOTE: Click on each image to display a larger image or a sequence of images.
1. Floor-Plan Overview
  - Get familiar with the floor-plan of where to install the   media box and where to pull the cables
   
2. Media Box Installation
  - Mark 1 foot from the floor to the media box bottom, and   mark the top box
- Hold the box into position and begin to drill holes
- Then drill in the screws on the left
- Finish up with drilling the screws on the right
   
  3. Locate, Identify, & Install Outlets
  - Locate the positions of the outlets by looking at the
  floor-plan and mark the wood B-blue, Y-yellow,
  G-green, or R-red. Note: The Y is for white and R for the   black cable
- Measure & mark the distance between the floor and the   outlet. About a foot (12") off the floor
- Hold the outlet in position
- Hammer the long nails to the top and bottom of the outlet   to hold it in place
   
  4. Setup Cable Wheel
  - Place a metal pole through the hole of the wheel
- Then use two wood stances and a ladder to hold the
  cable wheel in place
- Or manipulate the nails to be hooks and place the cable   wheel on them
   
  5. Label the Cable Temporarily
  - The purpose of using a permanent marker or tape to   label the cables is to identify which cable goes to which   room/place

   
  6. Review Floor-Plans Again
  - Review the floor-plan once again to decide where and   how to pull the cables to its destination area
 
   
  7. Pull Front Door Camera Cables
  - Pull the cable up the ladder and pull enough cables
  before climbing into the attic
  - Carefully swing the cable across the attic and feed the   cable through the drilled holes
  - Secure the cables with horse-shoe clamps as neccessary
  - Have another person to install the outlet (refer to step   3 for outlet installation)
  - Drill a hole (1.5" to 2") for the cable
   
  8. Pull Cables to Individual Destinations
  - Pull the cables from the cart wheel and up the ceiling
  - Drill hole for the cable, then feed the cable through and   begin pulling
  - Once pulled to the destinated room, split the cables with
  a utility knife or stripping tool
  - Strip the cables individually, some cables may stay   together, if unsure refer to the floor-plans
  - Drill holes and pull the stripped cables to its destination
  - After feeding the cables through the outlets, trim off
  extra cables, then go back to the media box room and
  cut the cables
   
  9. Pull Underground Cables
  - Click on the image to display the process of pulling the   underground cables
 
   
  10. Insert Cables Thru Media Box Tubes
  - Take 2 set of cables and feed them thru each tubes
 
   
  11. Relabel Cabels
  - Take new labels and replace the old ones with them
  - Purpose is to identify individual cables correctly
 
     
  12. Final Result
  - Organize the cables by curl them within the media box
 
     